Tondgouyan petrochemical complex is one of the most prominent complexes of its kind in the Persian Gulf region (petrochemical special economic zone).
Iran industrial network development company in the capacity of the main contractor was selected for implementation of the above plant covering installation and erection of mechanical and electrical equipment, instrumentation, heavy lifts operations, pre-commissioning and assistance in commissioning activities.
The completion duration of for construction of the plant was 22 months, utilizing approximately 4,500,000 man/hour up to project end.
Project | PTA2 |
Client | Tondgouyan Petrochemical Company |
Location | Petrochemical Free Special Economic Zone |
Starting Date | May 2003 |
Commissioning Date | Nov. 2005 |
Nominal Plant Capacity | 350,000 tons per year |
Total Weight of Erection | 9,649 metric tons |
Manpower Consumption | 4,356,260 Man-Hour |
Scope of Work | Construction & Erection Work |