24 November 2020
PTA - Phase 2

Tondgouyan petrochemical complex is one of the most prominent complexes of its kind in the Persian Gulf region (petrochemical special economic zone).

Iran industrial network development company in the capacity of the main contractor was selected for implementation of the above plant covering installation and erection of mechanical and electrical equipment, instrumentation, heavy lifts operations, pre-commissioning and assistance in commissioning activities.

The completion duration of for construction of the plant was 22 months, utilizing approximately 4,500,000 man/hour up to project end.

Project PTA2
Client Tondgouyan Petrochemical Company
Location Petrochemical Free Special Economic Zone
Starting Date May 2003
Commissioning Date Nov. 2005
Nominal Plant Capacity 350,000 tons per year
Total Weight of Erection 9,649 metric tons
Manpower Consumption 4,356,260 Man-Hour
Scope of Work Construction & Erection Work